19102 - Fitzsimmons Road Water Main Relay

 

Project No.:                                     19102

Construction Coordinator:           Seth Ricker    (414) 570-8200 ext. 38

Utility Engineer:               Brian Johnston    (414) 570-8200 ext. 24

 

Project Location Map

 

PROGRESS:

 

2019

 

AUGUST

 

August 16:The final water main connection is being completed today, and this will conclude the scheduled water main work.  Thank you for your patience and understanding while we work to improve our water main system.  The road restoration has started today as well with additional saw cutting and removals of the failed and broken concrete road sections.  To speed up the restoration process, the contractor will be mobilizing tomorrow, Saturday,  to start replacing curb and gutter, and as much of the concrete road section that they can complete tomorrow, with remaining work continuing next week.

 

Please note that the traffic pattern is still closed to through traffic, and two way traffic will be all on the north side of the road .  If you live on the south side of the road, you will have access to your driveway although you may need to cross temporary gravel.

 

 

JULY

 

July  25:Construction will begin Monday July 29th. Intitial mobilization and sawcutting to take place on Friday July 26th.  Work will take approximately 1 month to finish and the work zone is from Darlene Lane West 650 along East Fitzsimmons Road.