E. PUETZ ROAD WATER MAIN PROJECT

 

Project No.: 18102

Utility Engineer: Ron Pritzlaff  (414) 570-8200 ext. 24

Construction Coordinator: Seth Ricker    (414) 570-8200 ext. 38

Bid Date: 3/9/2018

Start Date: 4/9/2018

Contract Completion Date: 5/18/2018

 

 

PROGRESS:

 

2018

 

MAY

 

May 29: Restoration will continue as weather permits until project completion

 

May 21: For the week of May 21, restoration as weather permits

 

May 16-18: Restoration as weather permits hopefully by end of the week

May 15: Pavement Striping

 

May 14: Shouldering activities to place stone shoulder along edge of pavement

May 11: Pavement Marking

 

May 10: Asphalt Paving

 

May 9: Finish Grading

 

May 8: WisDOT to repair traffic signals

 

May 7: Proof roll and road repairs

May 1: Underground work has been completed

 

APRIL

 

April 24: Water service connections

 

April 21: Flushing the main

 

April 19: 12 Water main work

 

April 18: 12 Water main work

 

April 17: 12 Water main work

 

April 16: 12 Water main work

 

April 13: 12 Water main work

 

April 12: 12 Water main work

 

April 11: 12 Water main work

 

April 10: 12 Water main Connection

 

April 9: Traffic Control/Detour