E. PUETZ ROAD WATER MAIN PROJECT
Project No.: 18102
Utility Engineer: Ron Pritzlaff (414) 570-8200 ext. 24
Construction Coordinator: Seth Ricker (414) 570-8200 ext. 38
Bid Date: 3/9/2018
Start Date: 4/9/2018
Contract Completion Date: 5/18/2018
PROGRESS:
2018
MAY
May 29: Restoration will continue as
weather permits until project completion
May 21: For
the week of May 21, restoration as weather permits
May 16-18: Restoration as weather permits hopefully by end of the week
May 15: Pavement Striping
May 14: Shouldering activities to place stone shoulder along edge of pavement
May 11: Pavement
Marking
May 10: Asphalt
Paving
May 9: Finish
Grading
May 8: WisDOT to repair traffic signals
May 7: Proof roll and road repairs
May 1: Underground
work has been completed
APRIL
April 24: Water
service connections
April 21: Flushing the main
April 19: 12”
Water main work
April 18: 12”
Water main work
April 17: 12”
Water main work
April 16: 12”
Water main work
April 13: 12”
Water main work
April 12: 12”
Water main work
April 11: 12”
Water main work
April 10: 12”
Water main Connection
April 9: Traffic
Control/Detour