CUT-IN-VALVES PROJECT

 

Project No.:                                        17102

Utility Engineer:                               Ron Pritzlaff  (414) 570-8200 ext. 24

Construction Coordinator:           Seth Ricker    (414) 570-8200 ext. 38

Bid Date:                                             6/8/2017

Start Date:                                          7/31/2017

 

 

PROGRESS:

 

2017

 

SEPTEMBER

 

September  14: Work is substantially complete, however a few restoration items remain.  We are looking to finalize these items in the next couple of weeks.

 

AUGUST

 

August  14:          Contractor is mobilized to Chicago Road at Garden Place.  They will pre-dig at Garden Place Monday 8/14 and perform the installation operations on Tuesday 8/15.  Please keep in mind that water service will be interrupted from 8am -3pm.  Please give workers space be conscious of the signs, barrels, and change in traffic patterns.

 

August  3:            Asphalt repairs will take place at the locations of O’Brien Rd & 11th Ave, as well as Shepard Ave and Stone Gate Drive.

 

The contractor will mobilize operations to the area of Oakwood Road at Redwood Dr to start excavation on Monday August 7th.  Please look for notices of service interruption if you live in this area, and pay special attention to traffic control signage for your safety and the safety of others.

 

August  1:            The valve at the Intersection of E. O’Brien Rd. and S. 11th Ave. was successfully installed.  Thank you for your patience during the difficult water shutdown.  Pavement restoration and final cleanup will be forthcoming in the near future. 

The contractor has mobilized project operations to the area of Shepard Avenue and Stone-Gate.  They will be working on system modifications at this location for a couple of days.  No water shutdown is scheduled for this work.  If an emergency should arise we will communicate any service interruptions as soon as possible.

JULY

 

July  27:                Work on the Valve Cut-In Project will begin on Monday July 31, 2017.  The starting location will be at the intersection of 11th Ave and E. O’Brien Rd.  From there the contractor will move to locations in the following order:

                                                -S. Shepard Ave. and E. Stonegate Dr.

-E. Oakwood Road and Redwood Lane

-E. Oakwood Road and S. John Aaron Dr.

-S. Chicago Road and E. Garden Place

 

                                This work requires planned shutdown of the water main.  Please look for notices of water shut down times and dates handed out door to door 2 days prior to the shutdown.