SANITARY SEWER REHABILITATION PROJECT
Project No.: 16107
Utility Engineer: Ron Pritzlaff (414) 570-8200 ext. 24
Construction Coordinator: Seth Ricker (414) 570-8200 ext. 38
Bid Date: 11/11/2016
Start Date: 3/13/2017
Contract Completion Date: 6/2/2017
PROGRESS:
2017
JUNE
June
8: The project is substantially
complete. Some punch list items remain
before the project is finished.
MAY
May 24: Pavement marking in work areas over the next two weeks.
May 8: Monday 5/8 Lining operations will be on 5th avenue between Dexter and Depot during the day and E. Ryan Road between Chicago Rd and the RR tracks at night.
Tuesday 5/9 No work
Wednesday 5/10 Lining Operations on Nicholson Rd North of Sommers Dr.
Thursday 5/11 Lining operations on Nicholson Rd. North of Sommers Dr.
May 1: Monday 5/1: Night work on East Ryan Road East of Chicago Rd
Tuesday 5/2: Night work on Rawson Ave West of Howell Ave
Wednesday 5/3:Night work on Rawson Ave West of Howell Ave
APRIL
April 24: The week of April 24, sewer lining schedule:
Monday 4/24: Lining on Alton and Barton
Tuesday 4/25: Lining on Alton and 11th Ave Easement
Wednesday 4/26: Lining on Studio
Thursday 4/27: Lining on Studio
April 21: Lining will continue on 4th Avenue, Alton, and Elm Road.
April 17: The week of April 17, the contractor will commence
Phase Two operations consisting of the CIPP (Cured in Place Pipe) starting in
the Barton Oaks area.
April 13: Phase Two Customer Notice >>Phase Two Sanitary Main Lining Order Map<<
April 11: The contractor will be performing relay operation on Groveland Dr. at Jean Avenue.
April 10: The week of April 10, construction will commence on 5th Ave between Depot and Dexter then the crew will move to Groveland mid-week.
Pavement restoration will continue in Barton Oaks Subdivision followed by (old) Ryan Rd, Annette Pl, and Maple St.
Grass restoration is still a couple of weeks out.
Televising of Sewers will commence at repair areas in preparation of the Cured in place liner operation that will start the week of 4/17. This work will be done by Visu-Sewer.
No disruption of service will occur for televising operations.
April 3: The week of April 3, because work has been
slowed by inclement weather the contractor will continue work at Maple Street
and 5th Avenue.
MARCH
March 27: The week of March 27, the contractor will mobilize equipment to Carrollville area to perform work at Old Ryan Road East of Chicago Road, Maple Street, Annette Place, 5th Ave, and Dexter.
March 22: The contractor will be finishing Phase one in Barton Oaks Subdivision by weeks end, and mobilizing equipment out of the area. Restoration to be forthcoming.
March 15: Work will begin in Barton Oaks Subdivision starting on Studio Lane Thursday March 16.
March 13: Due to weather, the project will begin on Tuesday March 14 instead of Monday March 13.
March 13: The contractor, Advance Construction, will begin work on the Shepard Hills Elementary School property.