SANITARY SEWER REHABILITATION PROJECT

 

Project No.:                                        16107

Utility Engineer:                                 Ron Pritzlaff  (414) 570-8200 ext. 24

Construction Coordinator:              Seth Ricker    (414) 570-8200 ext. 38

Bid Date:                                             11/11/2016

Start Date:                                          3/13/2017

Contract Completion Date:            6/2/2017

 

 

PROGRESS:

 

2017

 

JUNE

 

June  8:                 The project is substantially complete.  Some punch list items remain before the project is finished.

 

MAY

 

May  24:               Pavement marking in work areas over the next two weeks.

 

May  8:                 Monday 5/8                        Lining operations will be on 5th avenue between Dexter and Depot during the day and E. Ryan Road between Chicago Rd and the RR tracks at night.

 

Tuesday 5/9                       No work

 

Wednesday 5/10              Lining Operations on Nicholson Rd North of Sommers Dr.

 

Thursday 5/11                   Lining operations on Nicholson Rd. North of Sommers Dr.

 

 

May  1:                 Monday 5/1:      Night work on East Ryan Road East of Chicago Rd

Tuesday 5/2:      Night work on Rawson Ave West of Howell Ave

 

Wednesday 5/3:Night work on Rawson Ave West of Howell Ave

 

 

APRIL

 

April 24:               The week of April 24, sewer lining schedule:

 

                                Monday 4/24: Lining on Alton and Barton

Tuesday 4/25: Lining on Alton and 11th Ave Easement

Wednesday 4/26: Lining on Studio

Thursday 4/27: Lining on Studio

April 21:               Lining will continue on 4th Avenue, Alton, and Elm Road.

 

April 17:               The week of April 17, the contractor will commence Phase Two operations consisting of the CIPP (Cured in Place Pipe) starting in the Barton Oaks area.

 

April 13:               Phase Two Customer Notice      >>Phase Two Sanitary Main Lining Order Map<<

 

April 11:               The contractor will be performing relay operation on Groveland Dr. at Jean Avenue.

 

April 10:               The week of April 10, construction will commence on 5th Ave between Depot and Dexter then the crew will move to Groveland mid-week.

 

Pavement restoration will continue in Barton Oaks Subdivision followed by (old) Ryan Rd, Annette Pl, and Maple St.

 

Grass restoration is still a couple of weeks out.

 

Televising of Sewers will commence at repair areas in preparation of the Cured in place liner operation that will start the week of 4/17. This work will be done by Visu-Sewer.

No disruption of service will occur for televising operations.

 

 

April 3:                 The week of April 3, because work has been slowed by inclement weather the contractor will continue work at Maple Street and 5th Avenue.

 

 

MARCH

 

March 27:            The week of March 27, the contractor will mobilize equipment to Carrollville area to perform work at Old Ryan Road East of Chicago Road, Maple Street, Annette Place, 5th Ave, and Dexter.

 

March 22:            The contractor will be finishing Phase one in Barton Oaks Subdivision by weeks end, and mobilizing equipment out of the area.  Restoration to be forthcoming.

 

March 15:            Work will begin in Barton Oaks Subdivision starting on Studio Lane Thursday March 16.

 

March 13:            Due to weather, the project will begin on Tuesday March 14 instead of Monday March 13.

 

March 13:            The contractor, Advance Construction, will begin work on the Shepard Hills Elementary School property.