FOREST HILL AVENUE WATER MAIN PROJECT
Project No.: 16101
Utility Engineer: Ron Pritzlaff (414) 570-8200 ext. 24
Construction Coordinator: Seth Ricker (414) 570-8200 ext. 38
Bid Date: 3/3/2017
Start Date: 5/1/2017
Contract Completion Date: 5/31/2017
PROGRESS:
2017
JULY
July
12: Due
to inclement weather, restoration repair is rescheduled for Friday 7/14.
July 10: The contractor, UPI, will be in on Wednesday to repair some of the restoration where settling has occurred.
JUNE
June
8: The project is substantially
complete. Some punch list items remain
before the project is finished.
MAY
May
30: Milling
of pavement will commence on Tuesday 5/30, with grading to follow
immediately. Paving of new road way will
be mid week.
May 24: 5/24 – 5/26 There will be no project operations for rest of week. The road will remain closed to Through Traffic.
May
22: Pavement work will occur mid-week,
weather permitting.
May 8: 5/8 – 5/12 Work on the water main continues. Road remains closed to through traffic
May 1: Monday 5/1: Work will start on Forest Hill, surveyors will be performing staking operations
Tuesday 5/2: Traffic control will be put out for proposed detour
Wednesday 5/3: Contractor will be saw cutting of pavement and driveways
Thursday 5/4: Excavation starts with water main shut down and initial connection.
Friday 5/5: Water main relay operations continue.